WIP & Little's Law Calculator
See how much work in process your line is carrying from just two numbers: throughput and flow time. Your numbers stay in your browser.
Average work in process
0 units
How this is calculated
Little's Law is the core relationship of flow. For a stable process, the average amount of work in process equals the average throughput multiplied by the average time a unit spends in the system.
The same law rearranges to describe flow time from a known WIP and throughput:
Reading it well
- Keep units consistent. If throughput is units per hour, flow time must be in hours, so WIP comes out in units. Mixing hours and days or minutes will give a wrong answer.
- Averages, not snapshots. Little's Law describes long-run averages for a stable system, not a single moment when the line just started or just stopped.
- Less WIP, shorter flow time. At a fixed throughput, cutting WIP directly cuts flow time, which is the whole point of pull and one-piece flow.
To see how flow time and value-added time relate, try the process cycle efficiency calculator and the manufacturing lead time calculator, or read the lean manufacturing guide.